Minister of Niger Delta Affairs, Mr. Usani Uguru |
The Minister of Niger Delta Affairs, Mr. Usani Uguru, on
Wednesday said the Federal Government has uncovered some shady deals by some of
the contractors that handled projects in the Niger Delta region between 2009
and 2015.
He said while some of the contractors made away with the
money paid them without appearing on the sites of the projects, some others
managed to implement 12 per cent of the projects they were paid for.
Uguru disclosed this to State House correspondents at the
end of the weekly meeting of the Federal Executive Council presided over by the
Acting President, Yemi Osinbajo, at the Presidential Villa, Abuja.
He said the discoveries were contained in a report of an
investigation carried out by the ministry on all contracts awarded and projects
carried out by the ministry from 2009 to 2015.
The late Umaru Yar’Adua and Goodluck Jonathan were the
Presidents of the country during the period.
The minister said the report revealed that over N423bn had
been expended in the region by the ministry alone, adding that the amount did
not include the sums expended by other intervention agencies.
“From this amount, projects execution rate has been at 12
per cent with an average completion rate of a project standing at five years.
The impact rate is eight per cent,” he said.
PUNCH
The minister said he sought and got the council’s approval
to make the report available to relevant government agencies in charge of
recovering government assets that were either misappropriated, misused or found
to be idling in some quarters.
He said while those who deserved sanctions would be
punished, others who needed to return to sites would be compelled to do so.
He said, “With this, it means all those who have accessed
government resources for one purpose or another must be compelled to make
adequate use of same, otherwise they will face the recommendation that goes
with such violations.
“That is our position concerning that report and we have
received council’s approval for that.
“Sixty per cent cost has been paid out to contractors with
12 per cent completion rate. Sixty per cent of the amount of money appropriated
which is N700bn, 60 per cent of that constitutes N423bn.
“To find that such money has been spent in that region with
the kind of work we see, shows that there is something tangibly and obviously
wrong with how procurement had been carried out in the ministry.
“The number of projects awarded was 427 and there is no
uniform action by each of the contractors. So, the measure of action to be
taken to address the shortfall of our expectations or commitment to contractual
agreements will be the determinant of what will be done.
“Those that require sanctions will be sanctioned. The
sanctions may not be uniform. It will be according to the measure of
liabilities hold by each of the contractors.
“Some will be compelled to return to site. Some, of course,
should be made to refund money, those who we have seen by their actions
displaying criminal intent by collecting money and not appearing at sites at
all.
“The report is not just all about punishing people. There
are also those who have performed well and are commended and the report
recommended that they should be encouraged to carry on in their contractual
commitments.
“The report has also recommended that sanction will be taken
against officers. There are rules. I don’t know if they will amount to purge.”